Grid reform, queue management and the future of connections

On this episode of the Hypercube Energy Podcast, Adam Sroka speaks with Catherine Cleary, Grid Connection Specialist at Roadnight Taylor, about why the UK grid connection process has become one of the biggest bottlenecks in energy infrastructure and what connection reform means in practice for developers, investors and the wider system.

Catherine shares her experience as an electrical engineer working across renewables, storage, demand and large industrial connections, explaining how grid projects move from application through to energisation. She outlines why the connections process has become increasingly complex, how queue reform is shifting the system from first come, first served to a more selective model, and why that creates both opportunities and uncertainties for the market.

The conversation also explores co-location, data centres, demand growth and the challenges of planning a grid for a much more distributed energy system. Adam and Catherine discuss where automation and AI could help, where human engineering judgment still matters, and why the sector needs to move faster on both process reform and physical delivery if it is going to meet wider clean power ambitions.

LISTEN ON SPOTIFYLISTEN ON APPLEWATCH ON YOUTUBE

Adam and Catherine cover:

  • Catherine’s role at Roadnight Taylor and how large projects navigate the grid connection process
  • Why the UK grid queue became unmanageable and what connections reform is trying to fix
  • Co-location, complex project structures and the growing challenge of connecting new demand
  • Where automation and AI could support the grid sector, and where they may create new risks
  • What progress needs to happen next to unlock faster delivery of energy infrastructure

Explore more with Roadnight Taylor:

Visit Roadnight Taylor’s website

Listen to the Connectology podcast

Connect with Catherine Cleary on LinkedIn

The Hypercube podcast sits down with leaders in the energy and utilities sectors to explore how data analytics can help businesses make smarter decisions and accelerate business growth.

CHAPTER MARKERS

Chapter markers

[00:00] Meet Catherine Cleary – Roadnight Taylor
[02:14] Why grid connections are complex and constantly evolving
[03:35] Developers, investors and navigating the grid process
[05:33] Co-location, complexity and changing project economics
[07:05] Why the grid connection process is no longer fit for purpose
[08:27] Understanding queue reform and the “sieving” process
[10:32] Winners, losers and market impact of reform
[15:06] Gate 1 vs Gate 2 and investment decision points
[17:50] Competition, uncertainty and investor confidence
[21:12] Can automation or AI fix grid connections?
[23:20] Why physical infrastructure is still the real bottleneck
[26:23] Trust, transparency and limits of automation
[31:57] Digital twins and the future of grid modelling
[37:35] Data gaps and the challenge of low voltage networks
[40:43] Clean Power 2030 – ambition vs reality
[43:54] Economics, investment and scaling infrastructure
[47:16] What meaningful progress looks like next
[49:25] Connectology podcast

TRANSCRIPT

Hypercube Podcast Transcript

Title: Grid reform, queue management and the future of connections

Host: Adam Sroka
Guests: Catherine Cleary

Adam (00:48)
Hello and welcome back to the HyperCube podcast. I am joined today by Catherine Cleary, who is a Grid Connection specialist from Road Knight Taylor in Glasgow, which is always great. Catherine, thank you for joining us. Would you like to explain your role, what you do, Road Knight Taylor, for our audience, please?

Catherine (01:06)
Yeah, sure. So I’m an electrical engineer and I’ve spent the last 15 years or so working primarily in the renewables industry, so connecting large projects to the grid. So that might be offshore wind farm, a large solar farm, an energy storage project, could be a data center or a hydrogen producer, so both demand and generation. And that’s what Roe.Taylor specializes in. So we’re a really niche consultancy who helps

those customers who are trying to connect to the grid to kind of navigate that process right from applying to the grid to actually building out and energizing that connection. And there may be problem solving issues which come up on operational projects. yeah, so that’s us.

Adam (01:48)
Very interesting, it? And it’s one of those, I often think like consultancies are essential in those parts of the universe where…

never sit still for long enough for like standardization and like automation. guess like in grid connection, it’s like engineering kind of financial systems engineering. how does that kind of nexus of skills play out and help customers and shape what you do?

Catherine (02:14)
Yeah, think, well, yeah, you’re definitely right. think that the consultant sort of thrives, don’t they, overly complex industry where everyone thinks I’m bit lost here. And it probably gives the game away if I’ve been doing the same thing for 50 years. And I still find it fascinating, which either means I’m a massive energy nerd, or it’s genuinely quite interesting and evolving. think

Yeah, grid connections in particular is a space which is really, really technical. So our power system is evolving incredibly. You know, we have moved away completely from the grid that we built in the 60s and we now have a far more diversified and distributed energy system. And so we keep building infrastructure, which is really interesting from an engineering perspective. But commercially, we’ve also carried on, you know, reforming and regulating that grid in a kind of really quite radically different steps. So I think that kind of commercial

technical and regulatory of combination is really hard for any one developer to sort of have covered on all fronts at any one time. So we tend to work with quite a lot of customers who are really established entities in this market. And so they might have that sort of legal commercial piece completely down, but they might be going, actually, we’re stuck on this particular technical issue. So we tend to kind of like coming in and sort of doing a bit of strategic problem solving.

and for customers on whichever of those three issues crops up.

Adam (03:35)
I guess like recent years, there’s been an influx of, especially in like, spend a lot of time in bears. There’s been an influx of new developers, like new funds that have, they’re trying to do things with maybe limited experience in deploying infrastructure and like actually trying to treat these as typical kind of financial investments and then having to rely quite heavily on third parties. How has that impacted your work? Do you see a lot of that?

Catherine (04:00)
Yeah, I mean, guess I could kind of break down. We work quite heavily with three different types of, I guess, end client. ⁓ And that might be what we call like a pure play developer. So that could be someone who develops battery storage or solar farms and they’re really good at developing, right? They go knock on the farmer’s door. They find good land. They get it through planning. You know, they get the grid connection and they’re basically packaging a project, which someone else who’s not very interested in doing that sort of slow

initial groundwork can then just come along, fund and build. So there’s kind pure play developers who tend to actually have really kind of core strengths in terms of understanding the grid connection process and the regulatory process, but might not have a big engineering team because they don’t build it. So there’s pure play developers. There’s the kind of owner operators, which are the big household names you probably think of, you know, say when you think of like a, I guess, know, RWE, you know.

SSE renewables, their office just down the road, haven’t they? You think, actually, these are the people who own wind farms or own battery storage projects. So those owner-operators will typically have significant in-house resource, but they might want an external party to do things like technical due diligence. ⁓ They’ll often be buying those schemes and wanting to make sure that they’re good. And then we’ve got the third, which is the institutional investors who are really just the money. And they’re sitting there going…

Catherine, I don’t really want to know about a voltage control problem or any of it. I just want to know, is this a good investment? Actually, does it have a bankable route into the grid connection process? So those three different sort of client types have three quite different asks.

Adam (05:33)
And I guess that you must, because there aren’t many vanilla projects left. There’s a lot more behind the meter, like the industrial commercials becoming a bigger and bigger focus. Yeah, co-location. like multi-party and all that kind of headache, that must get fun.

Catherine (05:44)
So location.

Yeah,

think two things happened. the commercials got harder. If we went back 10 years, we were in a world where rocks were just ending. So we have all the obligations to fix. If you get your solar farm through planning, it was quite a nice cushy commercial ride after that. That’s changed. So think it’s a real drive for developers to come up with more complex projects, which add revenue streams. So they’ve got a better route to market for that project. So that might be like co-location that often kind of say,

a solar farm and a battery together. Increasingly now it might be a data center and a battery and a wind farm together. So that kind of like adding elements to the mix and that increases the technical complexity of the grid connection that you need. That’s really interesting. I think the other thing is that actually, even if you did just want to build a nice vanilla wind farm now, the grid process that you are going to have to navigate is so much more complex. So the low hanging fruit.

of sort of saying, could I just cable back to the substation that’s near my project and connect? That’s kind of gone. The answer is no, it’s all full. And actually, you’re waiting for significant reinforcements or complex sort of negotiations about where new substations are going to be located. even if the projects were still simple, the grid route has become harder.

Adam (07:05)
Yeah, no, and I love it. like we have so Bridget Hartland-Johnson, who’s now a non-exec director for IPQ, she was on and she was talking about how she like, while she was at Austud developed the first co-located offshore wind farm bed site. Yeah. Because yeah, within the boundary of the site, it was co-located, but because of exactly that, the constraints on the grid and the way like you, how do you make this achievable? How do you do it? And I think it’s

Catherine (07:29)
And Austen is

still leading the charge on that. I probably give them a shout out because they have been doing some really interesting things about co-locating ⁓ VEST behind the off-to network that connects an offshore wind farm, is really interesting regulatory challenge.

Adam (07:41)
think, yeah, it’s just like fascinating to see, cause that’s like innovation of a different kind. It’s like sort of change what’s possible, not nest, there is new technology involved, but not necessarily like inventing new stuff, but just like doing stuff harder and differently to enable things that otherwise wouldn’t be.

Catherine (08:00)
think we’re going to see a lot more of that because, well, effectively, think like we can come onto it because you and I have discussed it a lot Adam, but the process is a bit broken. we’re going to talk about connections reform, I’m sure, but the grid connection process itself, you know, has effectively not become not fit for purpose. And therefore there’s been a clear driver for several years now to innovate that process. Not from a technical innovation perspective, but a process one.

And that on giving. Yeah. mean, think, so for anyone who doesn’t know connections reform, grid reform, essentially, I mean, we’re essentially reforming the grid queue. I guess it’s a quintessentially British problem, it? It’s all about queuing. ⁓ we’re moving from a world which was first come first served. So literally, if you wanted to connect your project, didn’t matter whether you were a hospital, a data center, or an offshore wind farm, you stick in your application to say,

know, network operator, please connect me. And you sit in the queue, you and you wait until you’re kind of at the top of the queue to be connected. And we’re moving from that world to a first sort of ready first connected. We’ve stuck in first ready and needed. And what that meant is that, you know, we’ve had so much queue growth over the years that effectively we’re now going back retrospectively, sort of sticking that queue in a sieve.

shaking the sieve and projects that were in the queue that don’t meet some of the criteria. So that might be the readiness part. if they haven’t got land ⁓ rights yet for their project, or maybe they haven’t yet got planning and they’re in a very kind of oversubscribed technology pot, then they fall out of the sieve and, know, sorry, goodbye, you don’t have a key position anymore. ⁓ And if you’re not needed, so that was the other kind of element. you know, well, who’s needed?

the government have very ambitiously come up with a plan as to what kind of generation types are needed and how much offshore wind do we need versus solar versus do we need any more gas and they’ve of set these these caps essentially and if your project is over that cap so we’ve got more battery in the queue than we need then some of these batteries fall away. So that piece of grid reform is pretty massive that that is basically the biggest reform we’ve done in the grid connection sector for the last 25 years so it’s

Yeah, it’s a big task. It’s been going on for really quite a long time. So we’ve been talking about this for sort of two and half years now. And I think it’s probably fair to say it’s not going very well.

Adam (10:32)
No, lots of strong opinions from everyone you meet and speak to because it has a huge impact, right? And, but it does like the way like you’ve just sort of summarized it there is really good. It does beg the question, is it un-understandable? Like what’s the definition of needed? What’s the definition of like, are they going to say, no, you can’t have your hospital for another few years. Like, and how does it like you go from, okay, suboptimal, but first in first out, like there we go. Everyone gets it.

Catherine (11:01)
It’s kind of a market as well. Like that was a clear process. Yeah.

Adam (11:05)
products where you can sell on your place and all this stuff to something that’s really just like, last the magic eight ball.

Catherine (11:13)
they would, at least they would absolutely disagree with the April analogy, I’m sure. They might disagree with my sieve. But the, suppose I do think it was needed. So, and I think that’s for a very, it’s like the analogy that I always use to my husband is it’s as if you go into a supermarket to do your shopping and you can already see that the queue is like,

Adam (11:24)
No, I agree that-

Catherine (11:35)
reaching around all of aisle one or something. So the first thing you do is you send your husband to go and stand in the queue whilst you do your shopping. And then by the time he gets to the queue, the place in the queue itself becomes valuable if the queue is big. So you get to this complete catch-22 situation where we want to reduce the size of the queue to make it a bit more manageable for the transmission operators to be able to plan the network. Because if they’ve got a queue, which is roughly speaking the numbers, we have about a system demand of about

50 gigawatts in this country. that means worst case day in the winter, everyone puts the kettles on all at once, maximum demand would be about 50 gigawatts. We usually expect to need 80 to 100 gigawatts worth of generation coming on in the next few years in order to be able to meet that with a broader range of intermittent generators. So if all of our generators were gas and nuclear, you’d need 50 gigawatts of generators to meet 50 gigawatts of demand. if it’s wind farms, solar farms need a bit more.

But it’s that kind of order of magnitude. And we had a queue, which is about 750 gigawatts. it had got out of hand. And that meant that every time, because you were putting your place in the queue and asking a network operator to give you a grid offer, they had to do all the network studies to work out, what do we need to reinforce or build to facilitate this 750th gigawatt? Even though they were going, well, this is bonkers. We don’t need 750 gigawatts. But they kind of did need to do something.

I think the needed part, so the ready part sort of makes sense. They did consult the industry. So I guess the grid industry is quite democratic in some ways. do it all via ⁓ CUSC modifications. So if you have a grid contract, you’re able to of vote in things to effectively elect a representative body that then kind of administer the CUSC. And anyone can suggest changes. So there was a lot of industry engagement on that.

the industry did kind get behind this whole concept of what’s a ready project and we settled on, well you need to have land rights. You need to be really specific that you’re trying to build a battery here. You can’t just say, I’m trying to build a battery somewhere. By the way, it might not be a battery, it might be a data center. you know, so they’ve locked it down to say, actually, it’s, it’s, you have to apply for specific technology, specific land, you have to have those land rights. That seems like a really good step. And then the needed part, I think, is more opaque and therefore more controversial.

⁓ The hospital, by the way, at the moment would never be told you’re not needed. So needed is a criteria which effectively only applies to generation. we demand, kind of we’re open to demand because I guess demand is the economy, The grid is here to serve demand. So ⁓ the needed part was to make sure we didn’t end up with a queue that was just filled with batteries or just filled with offshore wind farms because that doesn’t give us the mix we need.

Adam (14:21)
So plan a hospital to get your solar farm into the queue at the right stage. What a massive hospital.

Catherine (14:31)
⁓

I think that’s a level of innovation that I haven’t seen anyone adopt yet. I’m sure the NHS would be very happy with that.

Adam (14:37)
That feels like it could be worthwhile. might be onto something. I guess like, how long does, so if I’m in that, I just want to develop my site, I want to go and I don’t get it. How long does it take to like get, like come knocking on road like Taylor’s door? How long does it take to get that answer and support me? what, like what’s the impact? it, are people making go, no-go decisions based on, cause I’ve heard like they are. And how much can the needle get moved?

Catherine (15:06)
Yeah, so I mean, this is really fundamental because if you’re, if we sort of talk about the old days and the kind of new world post connections reform, ⁓ in the old days, you would come with your project. So you’ve got a project, you might not have planning consent for it yet, you know, but you’ve got a clear project definition, you know what you need in terms of your grid connection, and you make the application. Roughly speaking, within six months, so about three months, for them to kind of assess your application, they would give you a kind of commercial offer back that says we can connect you.

⁓ They can’t say no, by the way, they have to say how much and how long. So they could say, sorry, Adam, not till 2040, but they couldn’t say no, not at all. So they’ll tell you when would they be able to connect to you and how much would it cost? And you would make a decision about whether that was viable for your project. So that’s the kind of old world. ⁓ that, you know, if you then accepted that contract, you’re in a contract with, you know, it might be might have been with NISO, if it was a transmission connection or with your local distribution network operator, if it was a smaller distributed connection. ⁓

in a contract for that connection and they’re effectively obligated to deliver that connection. ⁓ In the new world, what we’re saying is we’re basically bringing in, we’re calling them gates. So, it’s like, you know, it’s like having to clear a hurdle. so in order to get that level of certainty and enter into a contract, you need to meet gate two. So gate one is just asking for a connection, but not being able to evidence that kind of ready or needed bit. In which case,

effectively get a holding position. You’re not in the queue, you’re just in a holding pen. In order to get that contractual and commercial certainty, you need a gate to offer. So there you need to have demonstrated that you’ve got your land rights, you need to have demonstrated that you’re strategically aligned with the generation pots to show that you’re needed. And then you would get a gate to offer. We’re currently in the middle of that process. So generators and demand customers are all waiting for the sieving of the queue, which has just taken place.

to kind of then precipitate out their new gate two offers. that’s a really, ⁓ and that’s where people are going to be making investment decisions. Ideally, once they’ve got their gate two offers to say, is this project still viable for me? So I did have a contract that said this, and now I’ve got a contract which says something slightly different. And I guess people are frustrated because I think, you know, the point of Connections Reform was to slim down that queue.

which should mean that everyone’s connections actually speed up. We’re no longer planning for 750 gigawatts. We’ve got a much more streamlined pipeline so we can do it more efficiently. So everyone was sort of told, well, you’re to get a new offer, but that offer should be better. ⁓ And that’s quite a nice pill to swallow. And I think we’ll maybe come onto it. But one of the challenges we’re seeing now is actually this process has taken a long time. It’s introduced a lot of uncertainty and a lot of delays and people might be getting worse offers. And that’s a real headache if you’re an investor.

Adam (17:50)
Yeah, because yeah, investors love uncertainty, right? I think it’s funny because I used to have the mental model of how like, lots of parts of the energy sector and development and building infrastructure is almost non-competitive. It’s much like airplanes, like airline safety, right? Like it has to be done so they will just collaborate on it and it all gets better. And it’s not really a competitive edge. You just have to have to be safe.

It’s a lot of energy developers are like, don’t care if you build your site faster. I just need to build my site fast. And, the gate process, especially in recent years, like when I talk to developers, like they’re fiercely competitive about trying to put their best foot forward and not share things. And I don’t think it’s become, it’s not gone totally the other way, but it’s funny how that’s had a material impact on the way. think a lot of the developers we’ve spoken to think about other parties within the industry.

Catherine (18:47)
guess connections reform creates winners and losers. It’s that shaking of the sieve. So we had to set some criteria that were who’s going to fall out of the queue. And that’s really controversial. So I think that process in itself was always going to create winners and losers and that can polarize the industry. think now that process is set and it’s kind of for better or worse, those criteria are what they are. I think there’s maybe a secondary kind of knock on impact, which is now if you’re still sitting in that sieve,

haven’t been kicked out of the queue, you’re in the new gate 2 queue. Actually, there is a concern that we’ve artificially reduced competition and that might not be a good thing for consumers. So we’ve sort of said, ⁓ we only need this amount of wind or we only need this amount of solar. And so when we’ve removed the rest from the queue. So does that mean actually those projects would have been like submitting bids in for CFD? So what you’ve done is arguably artificially reduced the size of the market. And that might mean that some of the projects you kicked out, might have been

cheaper or more deliverable. that is a controversial point as well. Is it going to have a market impact? I think that’s a little bit outside my wheelhouse to be honest as an electrical engineer. I think it’s really hard to, you can’t design the network for everyone, knowing that two thirds of might never come along and connect. yeah, it’s big problem.

Adam (20:04)
interesting.

And I guess like, it’s all current right, the other thing is it’s all happening right now. The system will reach steady state again. And it will kind of get back, but we just, that’s a way away and lots of money. ⁓

Catherine (20:18)
Yeah, I suppose

that kind of like sieving process, that is a one time action because what we’re doing is applying these new rules retrospectively going forwards, that criteria will just be there. You’ll have to clear that kind of gate too. So the new development world will optimise for that. And I think there’s room for, ⁓ you know, there’s a lot of potential. In fact, NISO are consulting right now on the, ⁓ they’re very unsexy, but the methodology documents that sit behind all of this.

and how they’ve kind of done that sort of shaking of the queue for this, we call it gate two to the whole queue exercise. So, know, effectively retrospectively applying that. We are now at a process where they’re sort of looking to say, was that a good way of doing it? Because by the way, when we do the next gate two window, maybe we could change some of these things. So like now is quite a good time for people to feed into that process. We like bugs for engagement.

Adam (21:12)
So you’ve spoken before about how this is probably falling behind other parts of the energy sector with regards to automation. Do you want to expand on that?

Catherine (21:22)
Yeah, yeah, definitely. And that’s probably much more, probably gone off on a Connections Reform rant. But yeah, I think the one of the process challenges, so Connections Reform has thrown it into light, you know, we’ve got this like volume challenge. you know, we’ve got large numbers of offers have to be produced, especially as part of this Newgate 2 process. And so I think one question which comes up again and again is

know, or can we automate stuff? Can we use AI? You know, like, why can’t we just like use technology to do this better, faster, just sort it all out? Yeah, exactly. And we probably, I think this will be good because I think we have quite different opinions on this, Adam. The, think I would differentiate between automation and AI. Would you agree?

Adam (22:04)
Ummm…

Catherine (22:07)
I guess I think from an engineering perspective automation could be just any piece of software, a system I set running to do a task automatically but maybe using really set rules that I’ve given it and it’s not trying to learn anything or evolve versus AI, which I think where you’re basically saying you learn and decide what the rules are yourself, AI, and then go nuts.

Adam (22:30)
Yeah, I, so I have a, I, I don’t agree because of a nuance in definitions of AI and things like that. So I usually start from a position of who cares. Like, I don’t care what, if it’s a magic like genie that does it, who gives, who cares, right? Because it’s, you want the outcome and you want it to be reliable and testable and all that. So if you do that, does it matter? And there is a bit of a misnomer and everyone, everyone sees AI and thinks

all AI will continually learn, but actually that is a very specific flavor of AI called reinforcement learning that’s quite hard to do and isn’t currently the de facto large language model AI, generative AI stuff. Like you would have to apply a reinforcement learner to do that. And I talked about with…

did a webinar yesterday and I talk about a joke about AAI is one of my favorite terms, artificial artificial intelligence, where it’s a human pretending. You get it in like these, there was a startup that went under recently and it turned out it was like a call center of 800 people that were just answering queries and like in a low cost country. And there’s a humanoidy robot startup that again, it’s like thousand people in the Philippines manually controlling these robots and stuff. so that AAI is an interesting term. And so what is happening today,

with AI learning and you get a lot of value from this. How often do you need it to learn? Do you need it to learn every minute or once a quarter? Because if it’s once a quarter, AI is good enough. Watch what happened and have humans inject new rules and processes, right? We will trend towards that continual learning stuff. And the other change that we’re seeing at moment with the kind of distinction of traditional machine learning and AI as in AI we’ve now rebranded to just mean large language models and…

generative AI is, I talk about how like some of the biggest, most well-funded, highest market cap companies that have ever existed, everyone like everyone I’ve ever met, a thousand people times the smartest person I’ve ever met, all work in one group at one of these companies. And they’re fighting this like Godzilla versus King Kong battle to build the best model. That’s unstoppable. That’s just happened. But that’s like the

Catherine (24:50)
Yeah. We

don’t necessarily need to let it design our electricity network.

Adam (24:55)
No, but that, but the, they’re building the kind of general engine that makes this the general brain smarter of it all. So you’re going to get, you’re going to get that increase for free. That’s going to happen whether you like it or not. So if you can build intelligent automation and leverage some of this tooling today and safely and securely and put the right bounds around it, it will just get better for nothing because like loads of

Daft VC and private equity companies are pouring billions into it. Anthropic just raised 30 billion dollars to fight in this fight, On top of it at 380 billion. So, is AI automation, continual learning? I would say no, but I think if we zoom back out to what most people mean, they mean plug it into the AI and it will just learn to do it. That I think is Daft.

Catherine (25:50)
Yeah, so, and I think we probably agree on that. And in terms of the reason for making that differentiation is that I think there are two different angles for how could this help in the grid sector? And I think, I I’ll make the first kind of controversial comment, which is that actually right now, I think the answer is no. And for two kind of specific reasons. One is that

AI cannot physically build anything. AI is not going to help us build new substations. It’s not going to be up there like stringing an overhead line in the midst of winter in Scotland. A lot of the critical path activities we have at the moment, the reason your hospital gets told it has to wait six years for its grid connection, which is not a good answer for the NHS, those are the critical path activities. A lot of them are physical manual tasks. AI just doesn’t help that.

AI can actively hinder it potentially, because if you break those critical paths down, you’ve basically got a task which is really hard about actually physically manufacturing and installing kit. And you’ve got a task at the beginning, which is basically around getting things like very large substations consented. I’m really ⁓ fiercely protective of the need for that to be a human, that’s engaging with a community that’s going to be affected. ⁓

we’ve seen, mean, AI has had an impact already in things like, you know, if it’s possible for one person to generate 50,000 objections to a substation. that can be huge. So, you know, it’s making sure we’re not kind of like swaying or in-duty influencing kind of, the democratic processes that are pretty fundamental. Cause I think, you know, we have to take people with us on this journey. Like you can’t just force someone to have a substation in their back garden. So I think AI doesn’t help with that physical kind of construction and build out of grid. I think the other thing is that, ⁓

I think we’ve spoken before, Adam, about the that the grid connection process itself, I guess it’s got harder, but it’s also got more opaque. So you’re basically asking for a grid connection. already feels a bit like it’s going into the black box of a very large, maybe national transmission operator who’s doing some studies in the background and coming out and saying, yeah, you can connect in 2037. this is the cost and this is why. And that can feel really

people say, why? I don’t understand why. And actually at the moment, even what you’ve got behind that is a power systems engineer who’s doing some network studying. they’re modeling. So they are, they’re using automated tools, but they are modeling what the grid is going to look like, what the impact of connecting your specific data center is, which elements of the grid need to overload and so on. And they’re doing that using sort of industry assumptions. So we have to have some assumptions about what the future network looks like.

current data, so how heavily loaded is the existing network, ⁓ and some kind of engineering rules about what we think is okay. And I think there’s a real value in being able to grill that engineer and say, look, if we flex one of those things with the answer change, you how confident are we about this thing? And I think if you tried to automate more of that process and remove the human content, you might be able to do it efficiently. You might get 10 % of it very, very wrong, but

the problem is you would lose the trust of the people who rely on it and they would say, how can I be confident this is right? No one’s able to explain it to me. And we’re kind of already in that situation at the moment. Developers are very frustrated because there’s been a bit of sort of embargo on the normal communication routes and you see that really affect industry confidence. So I think it’s interesting that there is something that possibly technically machine learning could help with, but it might be a hindrance in the short term.

Adam (29:33)
And it reflects like early on in my time in energy, I was building virtual power plants and we did some clever stuff for optimization. always say this all the time on the podcast, but optimization is a bit of a dirty word in energy, in my opinion, because it usually means sometimes we’ll turn it off. Like it’s not capital optimization, which is like, actually what’s the optimal set of decisions to be made. And we built these optimizers, like real messy boffin stuff, good fun, and then took it to the market. And this was a good…

five, six, seven years ago and no one wanted it. Like none of the developers wanted it for their, or the owner operators wanted it for their assets. Cause effectively they, if it did something wrong.

Catherine (30:11)
They didn’t know why or who to blame.

Adam (30:13)
Why

did they do that? Well, the highest peak in this N dimensional mountain ranges over there. So that’s why, whereas they want like, okay, give me a thousand if else statements. And then I can point at that when I’m on trial with the board of investors or whatever. And we’re seeing that change a little bit, but do you want to go through that system level? Like that is pretty terrifying. And we are seeing it play out in kind of non-energy big tech kind of AI stuff. Everyone’s hot for it. There’s an agenda being pushed.

But the winners, I think, are the people that are now saying, well, okay, I as the engineer, the software engineering is really interesting. It’s not the one thing everyone’s going for. I as the engineer, instead of sitting down and coding up the solution to the requirements that I’ve got for the day, I’m going to press a button and have a swarm of 20 agents battle it out to code that up, review each other’s work. And then when they’re done, which will be in about two minutes, they’re going to send me

something to review. And that is a nice process because they’re going to do two minutes is short, but they’re going to do maybe five or six days worth of coding. But there is, there is a right and a wrong answer that human can be the stage gate. And you’ll see people try and then automate the review process. I think that’s daft and we’re way off, but that kind of process might be interesting to see. But again, gently, gently, softly, softly, like what’s the smallest lowest risk.

environment to do that in. And we talked a little bit before about why haven’t we got a sandbox, a safe sort of digital twin, something that actually is backed and everyone can then engineer and test against that would allow us to do scenario planning and what ifs and modeling and optimization.

Catherine (31:57)
And

get and grow industry confidence. I like this idea of a digital twin. and I think it’s like, it’s a bit of a buzzword, isn’t it? But I think that a lot of people assume we have a digital twin. So effectively like a computer model that is simulating and reflecting what is happening on our national grid all the time. It’s just we’re saying we don’t, we don’t have that. We have a computer model, which is a power system approximation of

of the national grid, for example, and each distributer.

Adam (32:29)
Can I just say it, I did physics because triple E maths was too hard at uni, I thought, no tar, and I just did like, yeah, I did theoretical physics because the maths in triple E was too difficult. for people that aren’t aware, it’s really hard to model electrical systems.

Catherine (32:39)
Someone who did stuff about lasers.

Yeah. And we do use, I think that, you I’d like to make it clear. I’m not anti-automation in the sense that think engineers need to be writing out, you know, millions of lines of like, sheets and wraps and iteration in order to do a kind of power flow. You know, we have great, you know, we have great computer simulation programs, but the key thing is that they are snapshots. So effectively, like you’re building ⁓ a model, which is an approximation of the transmission network ⁓ at a moment in time. So that would include things like, you know,

which substations and overhead lines and so on. What’s the rating of those overhead lines? Have they been upgraded yet? imagine you’re sitting there in your perhaps National Grid Transmission in England and Wales. They own the infrastructure and they might have sort of, you know, some models which say, right, well in now in 2026, this is what the grid currently looks like. And in 2027, we’ll have done some more reinforcements. So we’ll have another model that shows what happens in 2027. And we’ll have some iterations and tunes we can play on those models to show at any moment in time, what would power flows look like?

won’t do every moment in time because that would be silly. So instead we’ll pick like, you know, what does it look like on a windy day in winter when there’s lots of wind farms in Scotland operating? What does it look like on a sunny day? What does it look like on a ⁓ kind of ⁓ a high pressure, you know, really cold snap? We know we’ve got no wind and we’re burning all the gas and obviously because those assets are located in different places that results in different power flows. So those are like snapshots. But what we don’t do is continually monitor

all flows on every asset in the grid, which is what you’d need to do to basically create that digital twin. And I think there is a question to say, should we be putting loads of effort into monitoring? So, know, actual kind of like monitoring units that are collecting that data so that in a couple of years time you could build that digital twin. And I think that like the, because we have that information on other areas in the market, you like if you did like

I know you guys do a lot of work on HyperCube, don’t you, on the energy market side. That data is there. We know exactly how much energy got sold by this producer for how much and so on. If that data was there for power flows on the power system, we’d be in a different place probably in terms of automation.

Adam (35:01)
Yeah. And I think the painful bit is there are almost certainly 20, 30, 40 year old computers sat in a field somewhere that has each individual element of that data on it for periods. Like something somewhere is doing it, there is a system monitoring something and you don’t need the perfect information if you have enough of it, if you have enough of a sort of confluence of that info, it’s just not connected. It’s all owned by private entities. It’s all like, or

It’s just not easily accessible because the digitalisation of the energy sector is a bit behind and we are starting to think about it.

Catherine (35:36)
Yeah, though, mean, again, possibly controversial opinion, though, we should maybe be quite thankful that some of that stuff is sat on a 40 year old computer that’s not connected to the internet in a field somewhere. You know, it is the reason that the national grid is quite unhackable at the moment because of that sort of like isolation. So I suppose if I was starting at this from a, know, with my very AI sceptic engineering brain saying, no, we should trust humans and, you know, and humans learn from this stuff. And, you know, and if we just

set AI at it, AI won’t notice all of the rubbish data and so on. If I had to pick where would I start, I wouldn’t start with the high risk, big transmission system. think there’s partly because they’ve got other stuff to do, Those transmission operators, they are going to be busy in the next 10 years building a huge amount of infrastructure. ⁓ And I think we can live with that snapshot model approach. think it’s a good 80-20, you put in so you get 80 % of the answer with 20 % of the effort. ⁓

So I think we leave the transmission system alone, but we were talking earlier about the opposite end of the spectrum. What about the low voltage networks, like the wires in the street outside your house? Those are things which we don’t have a digital twin of. We don’t even have a digital model of them half the time. It’s a paper drawing somewhere in a basement. That stuff, because we’re starting now from almost ground zero on some of that stuff, the digitisation of those records and so on,

could be really complicated to do and we’d be putting an awful lot of effort into just creating that snapshot version. So maybe on the lower voltage smaller stuff, we should be instead directing that effort into monitoring and saying, you know what, forget trying to an engineer to work out what’s the impedance of this bit of cable between my house and your house. Actually just stick some measuring on there. You’ve already got smart meter data, watch it and you can infer the impedance in real time.

So I think that could be really interesting. Digital twins are sort of low voltage, voltage, like the lower voltage distribution network.

Adam (37:35)
Yeah. I think, so the frustrating thing about that is imagine the smart meter roller actually worked and we actually did it and did a good job of that. Like that’s been such a shame that there’s other economies and countries and stuff doing it now, having learned some lessons from what’s happened here where it’s just not been like hard mandated and it’s not been left to private entities. And I think they, we,

It’s not a missed opportunity where there’s great data there is really useful, but even like working with DCC and stuff that they’re going through a digitization and a cloud adoption process and there’s barriers to entry there. you go to like the electrification of vehicles or heat and things like that. And there’s like, there’s supplies out there. We’ve had some of them on this podcast talk about how actually they’ve got like 250, 300,000 homes. They’ve got super over specced wifi connected meters for their EV charging fleet.

they have brilliant models of that low voltage network. And actually they can infer things about the transmission network because they cover such a broad, like they’ve got the physical model of what is where and they can say, right, well, this is outperforming that and here’s where it is. But how do you, there’s not really a mechanism for getting that out of their hands back into the kind of central knowledge base. ⁓

Catherine (38:46)
Yeah. And I do think you would need to link it up a little bit. The rest are missing bits of data there because we’ve got so much stuff that’s in people’s homes, but not very much that everyone’s homes connect into a secondary substation, know, we’d call it, which is, you know, probably like looks like sort of green cabinet, you know, maybe at the end of your street. And the, you know, no one’s monitoring that if you see what I mean. And then, and then the kind of upstream sort of primary substations that might be like, you know, one person of large village or, or small town. I think those

what can get lost is it can be quite easy to see like a national picture. The frequency, for example, gets monitored in lots of different places and it can sort of show you what’s happening in terms of ⁓ sort of the inertia on the system. That’s not actually the information we need to know. If you write to your local network operator and say, I’d like to put in a heat pump and an EV charger, please, can you tell me whether my, is my supply to my house good enough for that? They don’t care about the inertia of the network. What they care about is is the cable outside your house going to get too hot.

And is that transformer back at that secondary substation going to explode because you’ve overloaded it? So we need some extra bits of monitoring, which the network, the DNOs, they do do a lot more monitoring, but like you say, it’s not joined up with those other sources of information.

Adam (39:59)
And you’ve kind of hit the nail on the head in just that answer, isn’t it? Like how many parties, how many sort of entities have we just talked about there? Like DNO transmission, the homeowner, there’s so many, just, every time you add another person, it’s a Dunbar’s number of like, you can’t just, can’t even communicate because there’s too many of us trying to get things moving.

Catherine (40:16)
Yeah,

I think we could see network operators, so the distribution network operators, they might be some of the drivers behind that coordination. Smart meter data is really useful for them and they do get to see it in a of aggregated anonymized version. So I think there could be developments in that which could help move us forwards. But it’s a really interesting space because it’s basically less sexy than the big transmission infrastructure. So we don’t talk about it as much, but it’s definitely an area for improvement.

Adam (40:43)
but less risk. we’ve done away with a good reform. We’ve automated the whole energy system.

Catherine (40:52)
Adam has, I’d like…

Adam (40:54)
How far are or how, what about Clean Power 2030 then? Like that looks bonkers when you look at some of the numbers and some of the things that we need to achieve. Yeah, but like it feels like we’re maybe doing it.

Catherine (41:03)
The official hypercube.

Yeah, think people say clean power 2030, just to be clear, it’s a very clear labor government objective at the moment. Who knows whether that will change in future if we do have a different government. That’s a clear ambition to decarbonize the electricity sector. Electricity sector is already doing quite well in terms of decarbonization, but it is still a big goal to get to decarbonize by 2030.

know, we’ve set out this pretty ambitious plan that says, you know, yeah, we’re going to build more offshore wind, we’re going to build more solar, we’re going to build more renewables, and we’re not going to build any more gas unless it’s kind of got carbon capture or storage associated with it. Those are like big bold ambitions. And I think being pragmatic from a grid connection perspective, we’re not on track to meet that. But I don’t, I think, you know, is that natural? know, maybe it is good to go with a bold target. It focuses. And if we meet 80 % of that, 70 % of that,

I think we will have done an amazing job.

Adam (42:06)
Yeah, know it was like favourite books on strategy, good strategy, bad strategy talks about like objectives that are close to where you want to get to and just going for them because you and the classic example is the space race and the moon landing and saying, right, by the end of the decade, we’ll be on the moon.

Okay, then you just organize it gives everyone organizing principle to go after a thing and look at all that if they hadn’t landed on the moon or beat like the Russians in the race like well they still would had all these technological advancements so I totally think it’s a Valid thing to have tried to achieve but and it feels like like we might do it

Catherine (42:42)
I

mean, I think no one’s sitting down and saying this is impossible. I think it’s very hard to see how we would build all of that infrastructure in time for 2030 at the moment. There were several things which both the network companies and generators called for in terms of sort of reform to things like planning standards and stuff, which has been quite slow to come. So I think a lot of people would argue they’ve kind of been given the goal and not been given some of the tools to get there. But I think one thing which is really important to highlight is that

The Clean Power 2030 set this really clear target, which is having other benefits. That’s the side benefits of being bold and saying, we need to build this grid. Because in practice, you are now encouraging grid reinforcement, which is not just going to serve clean power technologies. It’s also, we need that grid to be able to power the data center in Slough, the hospital, actually kind of…

just giving the green light and more certainty to the industry that what we need to do now is build does have ancillary benefits. I think we’re wrong sometimes to overly simplify it and say, we’re doing this to be green. We’re not really doing it to be green. We’re doing it to keep lights on and keep the economy going.

Adam (43:54)
Yeah, there was a thing I saw years ago, I went to a talk for someone that they’d done a study and it was like bonkers numbers that were verifiable about how I think I’m going to get the specifics wrong, but it was a port they’d looked at and the sort of decarbonisation of this port and they basically found out or concluded that for every pound spent on that decarbonisation on green, they got 38 pound return in

ancillary benefits, not even on the initial money saving and all that, but on the local stuff. When you look at second and third order effects, local communities, the investment, all the changes that go around, it was just for a single port in the UK, they got 38 times return on the secondary effects. And I think we’ve not seen, I’ve not seen a study like that for the clean power stuff on the national scale. I think everyone’s got this warm fuzzy, we should be green, clean power.

feeling but I was told years ago and I think it’s a very pragmatic view of sort of net zero and climate change and I believe it is that like we’ve talked about some of these parties already but some of these people some of the people building this infrastructure are just money people they’re just like pension funds they’ve just got money make the money go up that’s it and so by doing it you’re just making these huge pots of money bigger right and that’s the very like financial kind of corporate evil overlord view of things but the day

everyone settles on the fact that like green electrons more profitable than any other kind. Wall Street will solve the problem for us because all the money will just start to flood in and we’ll get more challenge, more investment and the snowball will get rolling. And I believe that to be the case. And it won’t happen overnight. There’s like real constraints and physical things. But when that overbearing pressure investment appears, as you’ve seen with AI recently, like industries, governments, systems move pretty

pretty quickly, if with enough pressure.

Catherine (45:53)
Yeah, I suppose that moving quickly and being agile. Clean Power 2030 is perhaps not a particularly agile plan. It’s a static target effectively. So there’s a target for 2030 and there’s a target for 2035. And in the grid world, those translate to specific megawatt volumes of offshore wind of different types of generation, for example. think, know, we, one thing, you know, there’s the kind of the adage like

all plans are wrong, some plans are useful. Hopefully it’s been a useful tool in getting that kind of industry momentum going to say, yes, we need to build stuff. And also it’s a tool that we’ve used to revise the grid queue, but it is quite a coarse tool. think there’s a good Modo stat, was that the tool, sorry, the forecast for energy storage systems within Clean Power 2030, Clean Power 2030 basically says we need about, you know, sort of

25, 28 gigawatts of batteries by 2030 and then we don’t need any more. And they sort of unpicked that stat and went, well, that’s interesting. You we think you need a few more. what did you assume for like the cost of a battery? And then they said, oh, it’s about, you know, that cost is four times what the current market like per megawatt hour cost of a battery is. Plans are wrong because the data that they use, they’re out of date. Yeah. So I think one key thing is going to be how do we move forward? You know, we need more plans.

Adam (47:09)
immediately

Catherine (47:16)
And there is the next kind of update to that clean power plan from a networks and grid perspective is ⁓ the Strategic Spatial Energy Plan, SSCP. We love acronyms. And that again is like, it’s the next version of sort of saying how much wind versus solar versus batteries do we need and where do we need it? So it’s got that spatial element to it. I think it’s just what, yeah, it feels like an interesting time where

grid, NISO, ⁓ government are clearly quite comfortably kind of moving more towards that sort of centralized planning role and less towards that market solution that you mentioned. So it’ll be interesting to see which, which went out.

Adam (47:53)
I don’t mean it.

It’s so, it’s actually quite fun. It’s so easy to just sit and go that’s wrong and that needs done differently on that. But like, actually at the end of the day, there’s good reasons all this stuff happens the way it happens. And it is naturally messy. And it’s like, yeah, you make a plan, you do a thing and then the reality is different and everything has to move. And that all just takes time and it’s humans and it’s professionals. Like no one’s purposefully trying to do a bad job with any of it. Like it’s just a challenge, right? It’s a hard, complicated problem with lots of vested interest from

Competitive parties. I mean for you like what would meaningful progress for the next few years look like?

Catherine (48:30)
So I think we have to get faster at doing both the reforming of the queue. So this year is absolutely critical. We need to get those gate to offers out to customers so that they can progress with their commercial certainty and build projects. If you’re building a project, a large scale project connecting the transmission system, this side of 2030, you need to be starting ordering kit. Basically, you need to have your planning consent already. actually that pace of

pretty much business as usual activities but because of this big reform we’ve sort paused it all and we’ve got this backlog of work so we need to really be able to deliver at pace this year on the kind contractual side and then delivering the infrastructure at pace I think. So I think the kind of we need to get stuff kick-started into delivery now ⁓ and then I think we need to the next challenge is how do we be a bit more agile for those future plans.

Adam (49:25)
Hard one. This has been amazing. Thank you so much for coming on. I always ask the same question before I let anyone leave the room. If anyone in the audience wants to find out more about you or Road Knight Tailor or if there’s actually anything you want to promote or plug, where should we put

Catherine (49:41)
⁓ So, Road Knight Taylor, well, we have a podcast of our own. ⁓ the Connectology podcast, ⁓ which is ⁓ more of this great geeky stuff. ⁓ But we also, Road Knight Taylor have a whole series of sort of Connectology materials, so explainers and things like that. So, if anyone’s kind of quite interested in some of the geeky terminology or some of grid process stuff, there’s a lot of good stuff on our website that we try and disseminate for free because we think generally speaking.

everyone getting bit more educated about grid is fantastic for the industry. yeah, tune into the Connectology podcast.

Adam (50:14)
No, look, this has been amazing. think we could probably do this for another couple of hours and not get any further through the question list. So this has been great. Thank you so much for coming and seeing us here in Glasgow and look forward to the next episodes of Connectology.

Catherine (50:27)
Thank you so much for having me. It’s been pleasure.

Adam Sroka (50:31)
Thank you once again for listening to the Hypercube Energy podcast. As always, if you have any feedback or comments or you want to get involved, please get in touch. And if you want to find out more about what’s happening in data and AI across the energy sector, please join the Beyond Energy community and I look forward to speaking to you soon.

Do you have something to say about Energy and Data?

We always welcome new perspectives from leaders in the energy, trading and utilities sectors. If you fancy being a guest on the Hypercube podcast, drop us a message below and our team will be in touch.

AI FOR ENERGY

Socialise

Our Offices

Glasgow

Framework, 124 St Vincent St, Glasgow G2 5HF

Aberdeen

ONE Tech Hub is Schoolhill, Aberdeen, AB10 1JQ

Certificate No:428952023
Certificate No:428952023

Privacy Preference Center